Working to increase mobility and safety for drivers in Precinct 2.


CAPITOL HILL RD RECONSTRUCTION IS AWARD WINNING!
STATE AWARD presented for Best County Road.
A presentation was made in Commissioners Court for an award that was given to Texas Materials Group / Gulf Coast for the honor they received distinguishing the road reconstruction work they did for Precinct 2. A few weeks ago, the Texas Quality Asphalt Pavement Association (TXAPA) awards recognized the best-built county asphalt pavement project in the state.
Capitol Hill Rd was the entry of record.
Texas Materials Group Gulf Coast, selected by Precinct 2 to perform the road work, received the award.
Capitol Hill Rd is 1.1 miles and it was reconstructed with an 8” black base and a 2” Type D surface mix.
The work on Capitol Hill Rd was completed in September of 2025.
The project delivered an outstanding ride quality and a clean uniform appearance throughout.
The judging group recognized Capitol Hill Rd for the exceptionally smooth ride, consistent texture, well-constructed joints and edges and seamless transitions on and off the road.
Congratulations to Texas Materials Group / Gulf Coast for earning the TXAPA Asphalt Pavement award in the Best County Road category.



2025 ROAD BOND – Kidd Rd – Road Reconstruction
From near Stephen F. Austin Rd to Stidham Rd – COMPLETE
Distance: .99 miles


2025 ROAD BOND – River Plantation Rd – Road Reconstruction
From Covered Bridge to low water crosing – COMPLETE
Distance: 1.83 miles

2025 ROAD BOND – Mail Route Rd – Road Reconstruction
From FM 2854 to S. Pine Lake Rd – COMPLETE
Distance: 1.84 miles

2025 ROAD BOND – Old Hwy 105 W – Road Reconstruction
From SH 105 to FM 2854 – COMPLETE
Distance: 2.2 miles


2025 ROAD BOND – Kuykendahl
From Research Forest area to FM 1488 – In Progress


2025 ROAD BOND – Honea Egypt – Road Reconstruction
From Sendera Ranch Rd to FM 2854 – IN PROGRESS
Distance: 8.96 miles


2025 ROAD BOND – Hardin Store Rd – Road Reconstruction
Distance: 4.3 miles
Hardin Store Rd – Complete



2025 ROAD BOND – Rabon Chapel – Road Reconstruction
COMPLETE
4.2 miles – Widened where possible

Rabon Chapel Rd – COMPLETE

2025 ROAD BOND – Wright Rd – Road Reconstruction
From Decker Prairie Rd to Post Office in Pinehurst – COMPLETE
Distance: 2.42 miles
26 ft to 28 ft wide where possible.



2025 ROAD BOND – Goodson Loop – Road Reconstruction
From FM 1774 to FM 1774.
Distance: 3 miles
Widened where possible.


2025 ROAD BOND – Pine Ln – Road Reconstruction
Widened where possible.


2025 ROAD BOND – Capitol Hill Rd – Road Reconstruction
From McCaleb Rd to Rabon Chapel Rd – COMPLETE
Distance: almost 1.4 miles
Width – 28 ft


2025 ROAD BOND – Hardin Store Rd – Road Reconstruction
Phase 1 – from FM 2978 to Dobbin Hufsmith Rd – COMPLETE

2025 ROAD BOND – BUTERA Rd – Road Reconstruction.
From Nichols Sawmill Rd to Walnut Creek Rd. – COMPLETE
Distance: close to 2 miles


Road & Bridge Improvements & Maintenance


Additional – Road & Bridge Projects
Completed


Egypt Rd – Road Improvement, Added continuous turn lane- Repaving Project – COMPLETE

Lakeshore Dr. W. – Road Improvement – Repaving Project – COMPLETE


SANDY CREEK – Road Improvement – Repaving Project – COMPLETE

Miller Rd – Road Improvement – Repaving Project – COMPLETE

Nichols Sawmill Rd widening from Old Hockley Rd to Commerce St. – COMPLETE























Roadway and Traffic Signal Intersection Improvements.





3′ shoulders entire length of road; turn lanes added in front of the 2 new schools. – COMPLETE

Widened from Grand Pines to Nichols Sawmill Elementary (originally this was only 2 lanes) – COMPLETE

from Nichols Sawmill Elementary to Old Hockley Rd – COMPLETE